Document List by Topic

These documents on Commissioning (subtopic of Activity) are available:
(List events on Commissioning)

LIGO-Number Title Author(s) Topic(s) Last Updated
D1001575-v10 aLIGO SEI (Seismic) Sensor (Sensors) and Actuator (Actuators) Electronics Chains Jeffrey Kissel Assembly
Commissioning
Final Design
Seismic Isolation
20 Feb 2024
G1100431-v1 aLIGO Active Seismic Isolation Jeffrey Kissel Commissioning
Subsystem Test
Installation
Final Design
Seismic Isolation
15 Sep 2023
G1500623-v6 aLIGO, CAL, Official Advanced LIGO Sensitivity Plots Jeffrey Kissel et al. Commissioning
Calibration
23 Jun 2023
P1200087-v58 Prospects for Observing and Localizing Gravitational-Wave Transients with Advanced LIGO, Advanced Virgo and KAGRA LIGO Scientific Collaboration et al. Commissioning
Astrophysics / Multi-messenger
Compact Binaries
GW Bursts
01 Aug 2022
G1300086-v2 HAM6 Coordinate System Definitions Jeffrey Kissel System Engineering
Commissioning
Modelling
Sensing and Control
Final Design
Seismic Isolation
Integration
Suspensions
08 Mar 2015
T070107-v7 BOSEM Test Specification Stuart Aston et al. Commissioning
Suspensions
09 Mar 2016
T0900023-v2 (OMC) DC (DCPD) readout (Power) Normalization (Linearization) Sam Waldman Commissioning
Sensing and Control
25 Jun 2021
D1500308-v1 Common Mode Servo Card, 40m Revisions Rana Adhikari et al. Commissioning
Sensing and Control
11 Dec 2015
T070082-v1 LIGO I mirror scattering loss by microroughness Hiro Yamamoto Commissioning
Core Optics
06 Apr 2009
G1400001-v3 The Status of Advanced LIGO: Light at the End of the Tunnels! Jeffrey Kissel et al. System Engineering
Commissioning
Input Optics
Data Acquisition System
State Control and Monitoring
Sensing and Control
Public Talk / Colloquium
Seismic Isolation
Laser Systems
Core Optics
Integration
Auxiliary Optics
Suspensions
17 Aug 2016
T1500120-v1 Suggested Improvements to SEI / SUS Designs for aLIGO Upgrades Jeffrey Kissel et al. System Engineering
Commissioning
Sensing and Control
Seismic Isolation
Conceptual Design
Core Optics
Upgrades
Auxiliary Optics
Suspensions
26 May 2016
G1401291-v3 aLIGO HSTS Damping Loop Design Comparison Jeffrey Kissel et al. Commissioning
Modelling
Sensing and Control
Integration
Suspensions
25 May 2016
G1401290-v1 aLIGO HSTS "Level 2" Damping Loop Design Betsy Weaver et al. Commissioning
Modelling
Sensing and Control
Seismic Isolation
Integration
Suspensions
25 May 2016
G1400151-x0 aLIGO HLTS "Level 2" Damping Loop Design Jeffrey Kissel Commissioning
Modelling
Sensing and Control
Suspensions
25 May 2016
G1600447-v3 FINESSE - Numerical Simulations for Optical Design and Commissioning Daniel Toyra et al. Commissioning
Modelling
17 May 2016
P1500237-v11 GW150914: The Advanced LIGO Detectors in the Era of First Discoveries LIGO Scientific Collaboration et al. Commissioning
04 Apr 2016
G1600276-v1 Automation of the ISS second loop: issues and mitigations Kiwamu Izumi Commissioning
15 Feb 2016
G1600150-v1 H1 Calibrated Sensitivity Spectra Oct 24 2015 (Representative for O1) Daniel Sigg Commissioning
Sensing and Control
Calibration
Detector Characterization
18 Jan 2016
G1600151-v1 L1 Calibrated Sensitivity Spectra Oct 24 2015 (Representative for O1) Daniel Sigg Commissioning
Sensing and Control
Calibration
Detector Characterization
18 Jan 2016
P1400074-v5 Self Amplified Lock of a Ultra-narrow Linewidth Optical Cavity Kiwamu Izumi et al. Commissioning
Modelling
Basic R&D
Integration
08 Jan 2016
G1501380-v1 Ideas for RF Glictch Identification / Mitigation Koji Arai Commissioning
Sensing and Control
12 Nov 2015
T1300690-v1 TwinCAT EPICS IOC Documentation Maggie Tse Commissioning
Sensing and Control
23 Oct 2015
E1101149-v19 HEPI Pier Components - LHO Eric Allwine et al. Commissioning
Seismic Isolation
21 Oct 2015
G1501223-v3 H1 Calibrated Sensitivity Spectra Oct 1 2015 (Representative for Start of O1) Jeffrey Kissel Commissioning
Sensing and Control
Calibration
Detector Characterization
19 Oct 2015
G1401213-v1 Update on the charging issues at aLIGO Borja Sorazu Commissioning
Meeting
Suspensions
29 Sep 2015
T1400535-v2 Experience with discharging the ETMY test mass at LHO in August 2014 Gerardo Moreno et al. Commissioning
Vacuum
Suspensions
29 Sep 2015
T1400182-v1 Simulations of effects of LLO mode-mismatches on PRFPMI error signals Charlotte Bond et al. Commissioning
28 Sep 2015
G1500823-v4 H1 Calibrated Sensitivity Spectra Jun 9 2015 (Best for ER7) Jeffrey Kissel Commissioning
Sensing and Control
Calibration
Detector Characterization
09 Jul 2015
G1500711-v1 Status of LIGO Daniel Sigg Commissioning
17 Jun 2015
G1500645-v3 Sensing and control problems in low finesse cavities, or "how (not) to hop" Paul Fulda et al. Commissioning
Sensing and Control
02 Jun 2015
G1500668-v1 Squeezing now and in the future: the road to 10 dB Katherine Dooley et al. Commissioning
Requirements
Sensing and Control
Meeting
Basic R&D
Integration
Squeezer
01 Jun 2015
G1500694-x0 Keeping a good lock Keita Kawabe Commissioning
Meeting
Integration
20 May 2015
T1300552-v3 OMC DCPD characterization for aLIGO transition William Korth et al. Commissioning
Sensing and Control
16 May 2015
G1500643-v1 Lessons learned from commissioning of Advanced Detectors Daniel Sigg Commissioning
16 May 2015
G1500414-v4 aLIGO commissioning update Lisa Barsotti Commissioning
16 Apr 2015
G1200070-v2 Ideal Order/Contents of aLIGO Triple SUS Testing / Commissioning Jeffrey Kissel Assembly
Commissioning
Requirements
Subsystem Test
Installation
System Test
Integration
Suspensions
08 Mar 2015
L1300207-v1 aLIGO OMC installation/commissioning notes William Korth Commissioning
Sensing and Control
Installation
06 Mar 2015
D1300606-v2 ALS Faraday Isolator Fixed Base Bram Slagmolen et al. Commissioning
Sensing and Control
05 Mar 2015
D1300611-v1 ALS Faraday Isolator Adjustable Spacer Bram Slagmolen Commissioning
Sensing and Control
05 Mar 2015
D1300610-v1 ALS Faraday Isolator Adjustable Base Bram Slagmolen Commissioning
Sensing and Control
05 Mar 2015
T1200429-v1 Arm Length Stabilisation - FIBRE Phase-Locked-Loop Bram Slagmolen et al. Commissioning
Sensing and Control
04 Mar 2015
E1100822-v33 aLIGO BSC-ISI, Cables inventory and Installation Location Vincent Lhuillier Commissioning
Seismic Isolation
26 Feb 2015
D1500062-v1 CARM handoff signal diagram Eleanor King Commissioning
Sensing and Control
11 Feb 2015
P1400234-v3 In-situ Characterization of the Thermal State of Resonant Optical Interferometers via Tracking of their Higher Order Mode Resonances Chris Mueller et al. Commissioning
Sensing and Control
09 Feb 2015
D1300777-v1 aLIGO Pcal Tooling, Viewport Beam Target Assembly Craig Conley Commissioning
Installation
Auxiliary Optics
05 Feb 2015
G1400710-v1 L1 TransMonEY Telescope Focal Tuning Results Adam Mullavey et al. Commissioning
Auxiliary Optics
21 Jan 2015
G1401271-v1 Optical lever Laser Diode Laser glitches and repairs Suresh Doravari Commissioning
Suspensions
07 Jan 2015
E1400218-v2 HTTS Test Reports Bram Slagmolen Commissioning
Sensing and Control
27 Nov 2014
E1000496-x0 aLIGO SUS BSFM Testing and Commissioning Documentation Derek Bridges et al. Assembly
Commissioning
Subsystem Test
Suspensions
25 Nov 2014
G1401257-v1 Initial alignment at LHO: status and plans Kiwamu Izumi et al. Commissioning
28 Oct 2014
G1401253-v1 LHO Interferometer locking status (Commissioning F2F meeting) Alexa N Staley et al. Commissioning
28 Oct 2014
T1400672-x0 Report from the Commissioning Workshop on Suspensions at Virgo Jeffrey Kissel et al. Commissioning
Modelling
Installation
Seismic Isolation
Meeting
Basic R&D
Integration
Suspensions
21 Oct 2014
G1401248-v1 Photos From Oct 2014 SEI & SUS Commissioning Workshop @ VIRGO Jeffrey Kissel et al. Commissioning
Seismic Isolation
Vacuum
Suspensions
21 Oct 2014
E1400312-x0 Electronics and Optics Change Request from the HIFO-XY Test Daniel Sigg Commissioning
19 Oct 2014
T1300359-v1 How to Handle Small Optics Daniel Sigg Commissioning
14 Oct 2014
T1400633-x0 Designing a frequency offset locking loop for 40m prototype Arm Length Stabilization System Akhil Reddy et al. Commissioning
Sensing and Control
29 Sep 2014
T1400585-v1 Matrix calculations for the angular control of H1 OMC Koji Arai et al. Commissioning
Sensing and Control
04 Sep 2014
G1401078-v1 Advanced LIGO Commissioning Overview Peter Fritschel Commissioning
27 Aug 2014
G1100693-v5 Ideal Order/Contents of aLIGO QUAD Testing / Commissioning Jeffrey Kissel Assembly
Commissioning
Requirements
Subsystem Test
Installation
System Test
Integration
Suspensions
22 Aug 2014
T1300155-v2 Alignment sensing control signals of DRMI Keiko Kokeyama et al. Commissioning
Squeezer
15 Aug 2014
T010061-x0 ISC Electrooptic Shutter: Angle and Temperature Tolerance Jameson Graef Rollins et al. Commissioning
Sensing and Control
14 Aug 2014
P1400148-v1 Techniques for Resonant Optical Interferometry with Applications to the Advanced LIGO Gravitaional Wave Detectors. Chris Mueller Commissioning
Input Optics
State Control and Monitoring
Sensing and Control
Final Design
Laser Systems
04 Aug 2014
G1400785-v1 Notes on DRMI locking at LLO Kiwamu Izumi Commissioning
31 Jul 2014
D1300608-v1 ALS Mad-City Labs Spacer Bram Slagmolen Commissioning
Sensing and Control
08 Jul 2014
D1300607-v1 ALS Mad-City Labs Base John Miller et al. Commissioning
Sensing and Control
08 Jul 2014
E1300803-x0 Changes Resulting from the L1 DRMI Testing Peter Fritschel et al. Commissioning
Integration
20 Jun 2014
E1400300-x0 Changes Resulting from Input Mode Cleaner Testing Dennis Coyne Commissioning
Integration
19 Jun 2014
E1201027-v1 ECR: Replacement of the coil-series resistors in the HAM-A coil drivers David Feldbaum Commissioning
Requirements
Input Optics
Sensing and Control
Final Design
Upgrades
Suspensions
19 Jun 2014
G1301192-v3 Simulink/Front Model & MEDM Screen Mods from ECR E1300578 Jeffrey Kissel Commissioning
Sensing and Control
Suspensions
19 Jun 2014
G1300138-v1 Noise Budget Infrastructure Christopher Wipf Commissioning
19 Jun 2014
G1301269-v1 DRMI Noise Budget Denis Martynov Commissioning
19 Jun 2014
G1400651-v1 DRFPMI NB snapshot Christopher Wipf Commissioning
19 Jun 2014
E1200044-x0 aLIGO BSC-HEPI, LHO BSC6: Phase I Testing Report Vincent Lhuillier Commissioning
Seismic Isolation
18 Jun 2014
E1200043-x0 aLIGO BSC-HEPI, LHO BSC8: Phase I Testing Report Vincent Lhuillier Commissioning
Seismic Isolation
18 Jun 2014
E1100740-v7 aLIGO BSC-ISI, Seismometers Installation Location Vincent Lhuillier Commissioning
Seismic Isolation
18 Jun 2014
E1100741-v1 aLIGO BSC-ISI, Actuators Installation Location Vincent Lhuillier Commissioning
Seismic Isolation
18 Jun 2014
T1300126-v1 IMC Autolocker Adam Mullavey et al. Commissioning
Sensing and Control
18 Jun 2014
E1300495-v3 LLO DRMI In-air Check List Valery Frolov Commissioning
Integration
18 Jun 2014
T1400011-v1 Integration Testing: Systems meeting discussion, 15 Jan 2014 Peter Fritschel Commissioning
Integration
18 Jun 2014
T1300991-v1 PRMI Locking Procedure Ryan DeRosa et al. Commissioning
Integration
18 Jun 2014
T1300174-v2 Commissioning Advanced LIGO’s HIFO-Y Daniel Sigg et al. System Engineering
Commissioning
Integration
18 Jun 2014
D1400191-x0 FI2 635S Micro Laser Fermion II Michael Vargas Commissioning
Subsystem Test
18 Jun 2014
E1400002-v1 ECR - Acquisition of FSS RFPD DC signal Kiwamu Izumi Commissioning
Integration
16 Jun 2014
T1400368-v1 Advanced LIGO Operations Commissioning Plan Peter Fritschel et al. Commissioning
11 Jun 2014
P1300001-v1 [Thesis] Multi-Color Interferometry for Lock Acquisition of Laser Interferometric Gravitational-wave Detectors Kiwamu Izumi et al. Commissioning
Thesis/Dissertation
10 Jun 2014
G1400529-v2 Commissioning of Advanced LIGO Kiwamu Izumi Commissioning
Integration
25 May 2014
T1400298-v1 Simulation study for aLIGO lock acquisition Kiwamu Izumi et al. Commissioning
Modelling
Meeting
Integration
03 May 2014
D1002969-v9 Broadband Photodetector (BBPD) Schematic Matthew Evans Commissioning
Sensing and Control
Preliminary Design
01 Apr 2014
G1400137-v1 ISI tuning vs interferometer states and seismic input Lisa Barsotti Commissioning
25 Feb 2014
T1400047-v1 Power Recycling Probe Experiment Proposal Chris Mueller Commissioning
Sensing and Control
06 Feb 2014
E1300966-v1 aLIGO IO H1 EOM in-situ characterization Kiwamu Izumi et al. Commissioning
20 Jan 2014
T1300629-x0 SEI Guardians Brian Lantz Commissioning
State Control and Monitoring
Seismic Isolation
20 Jan 2014
T1300435-v1 Suspension Module Guardian Design Jeffrey Kissel et al. Commissioning
State Control and Monitoring
Preliminary Design
Suspensions
20 Jan 2014
T1200307-v4 Early aLIGO Configurations: example scenarios toward design sensitivity Lisa Barsotti et al. Commissioning
15 Jan 2014
T1300954-v2 Investigation of beam clipping in the Power Recycling Cavity of Advanced LIGO using FINESSE Charlotte Bond et al. Commissioning
Core Optics
16 Dec 2013
T1200437-v3 Advanced LIGO Interferometer Integration Peter Fritschel et al. Commissioning
Integration
11 Dec 2013
G1200632-v3 Towards Applied Heirarchical Control Jeffrey Kissel Commissioning
Sensing and Control
Seismic Isolation
Preliminary Design
Suspensions
11 Dec 2013
G1300530-v2 The aLIGO Guardian Jeffrey Kissel Commissioning
State Control and Monitoring
Preliminary Design
11 Dec 2013
G1300561-v1 aLIGO BSFM "Level 2" Damping Loop Design Jeffrey Kissel Commissioning
Suspensions
11 Dec 2013
G1300537-v3 aLIGO QUAD "Level 2" Damping Loop Design Jeffrey Kissel Commissioning
Suspensions
11 Dec 2013
D1300778-v2 aLIGO Pcal Tooling, Viewport Beam Target Craig Conley Commissioning
Installation
Auxiliary Optics
07 Dec 2013
G1300909-v1 Mode matching investigations at LLO Lisa Barsotti et al. Commissioning
Sensing and Control
06 Sep 2013
E1300656-v1 Electronics and Optics Change Request from the HIFO-Y Test Daniel Sigg Commissioning
03 Sep 2013
G1300830-v1 sustools.py, a Python module for SUS Mark Barton Commissioning
Suspensions
12 Aug 2013
G1300524-v1 The Arm Length Stabilisation System for Advanced LIGO Lock Acquisition Adam Mullavey et al. Commissioning
Sensing and Control
09 Jul 2013
G1300719-v3 Performance of the Advanced LIGO Input Optics Chris Mueller Commissioning
Input Optics
Subsystem Test
Public Talk / Colloquium
Integration
09 Jul 2013
E1300578-v1 ECR: Topology Changes to SUS models as a result of ISC Informed Interaction Jeffrey Kissel Commissioning
Change Control
Suspensions
02 Jul 2013
T1300558-v1 L1 DRMI Measurements: a checklist Peter Fritschel et al. Commissioning
System Test
18 Jun 2013
G1300624-v1 Identifying and mitigating scattered light noise in LIGO - GEO scattering workshop Robert Schofield Commissioning
10 Jun 2013
D1300513-v1 HIFO-Y(Half Interferomter Y) expected power budget for initial alignment Kiwamu Izumi Commissioning
06 Jun 2013
G1300576-x0 Building up a commissioning network Lisa Barsotti Commissioning
20 May 2013
G1300554-v1 First Lessons from the Advanced LIGO Integration Testing Daniel Sigg Commissioning
16 May 2013
G1300533-v1 Status update of aLIGO lock acquisition simulation (20130503) Kiwamu Izumi Commissioning
03 May 2013
G1300119-v2 Friendly Power Shutdown for LLO Corner Buildings David Kinzel System Engineering
Data and Computing
Commissioning
Input Optics
Data Acquisition System
Sensing and Control
Seismic Isolation
Policies
Vacuum
Laser Systems
Core Optics
Auxiliary Optics
Observatory Facilities
Suspensions
11 Apr 2013
G1300434-v1 Update from the AEI 10m Prototype Tobin Fricke Commissioning
Public Talk / Colloquium
Installation
07 Apr 2013
G1100769-v2 QUAD Testing Outline, Phase 2B Jeffrey Kissel et al. System Engineering
Commissioning
Fabrication
Subsystem Test
System Test
Core Optics
Basic R&D
Auxiliary Optics
Suspensions
25 Mar 2013
T1300158-v2 Arm cavity geometry for H1 ALS test with X and Y arm Keita Kawabe Commissioning
Sensing and Control
Core Optics
18 Mar 2013
T1100080-v3 Commissioning Advanced LIGO's First Arm Cavity Daniel Sigg et al. System Engineering
Commissioning
Integration
17 Mar 2013
G1300050-v3 Output Mode Cleaners Keita Kawabe et al. Commissioning
28 Jan 2013
G1201266-v1 Smoke, Mirrors, Big Bangs And Big Scientific Payoffs: An outline for using an interferometer network to conduct astronomy. Cristina Torres et al. Commissioning
Public Talk / Colloquium
Basic R&D
Detector
Education, Outreach
Data Analysis
13 Dec 2012
T1200450-v2 Cavity alignment fluctuations in the H2 One Arm Test Lisa Barsotti Commissioning
03 Dec 2012
G1200753-v1 aLIGO H2 One Arm Test Update Keita Kawabe et al. Commissioning
Detector
03 Dec 2012
G1201211-v1 Flow diagrams for HEPI actuators, bleed and operate mode Brian Lantz et al. Assembly
Commissioning
Seismic Isolation
26 Nov 2012
D1201460-v1 aLIGO AOS Oplev & Pcal Installation Layout, Y-END Stations Craig Conley Commissioning
Installation
Integration
Auxiliary Optics
12 Nov 2012
D1201459-v1 aLIGO AOS Oplev & Pcal Installation Layout, X-END Stations Craig Conley Commissioning
Installation
Integration
Auxiliary Optics
12 Nov 2012
G1201058-v1 Cavity Error Calibration Notes for a Damped Triple Pendulum LVC Commissioning
Basic R&D
02 Oct 2012
T1200424-v1 Setting up the Physical Environment Monitoring System for Advanced LIGO Maggie Tse Commissioning
29 Aug 2012
T1200285-v1 Description of the Sensor Correction FIR & IIR Filter Components Brian Lantz Commissioning
Seismic Isolation
06 Jun 2012
T1200200-v1 H2 One Arm Test Beam Geometry Keita Kawabe et al. Commissioning
07 May 2012
T080144-v1 The Enhanced LIGO Output Mode Cleaners Sam Waldman Commissioning
Sensing and Control
24 Apr 2012
T1200172-v2 Installation and testing of L1 PSL table legs Riccardo DeSalvo et al. Commissioning
Laser Systems
15 Apr 2012
E080228-v1 L1 HAM6 ISI Mass Layout (As-Leveled) Michael Meyer Commissioning
Seismic Isolation
01 Apr 2012
T0900285-v2 L1 HAM6 ISI eLIGO Final Performance Measurements (March 24 2010) Jeffrey Kissel Commissioning
Requirements
Final Design
Seismic Isolation
12 Mar 2012
P1200020-x0 Design, Control, and Performance of a Prototype Advanced LIGO Single-Stage Seismic Isolation Platform Jeffrey Kissel et al. Commissioning
Requirements
Subsystem Test
Final Design
Seismic Isolation
27 Feb 2012
T0900508-v1 LLO OMC Mode Matching Katherine Dooley Commissioning
Modelling
Conceptual Design
Auxiliary Optics
23 Feb 2012
G1101190-v1 CDS Meeting: Daily News Rana Adhikari et al. Commissioning
Data Acquisition System
27 Oct 2011
G1101178-v1 Research activities at the Caltech 40m prototype Koji Arai Commissioning
Sensing and Control
System Test
Basic R&D
24 Oct 2011
T1100443-v1 H1 HAM6 vent plan for cleaning eLIGO OMC Keita Kawabe Commissioning
15 Aug 2011
G050111-v1 Summary of recent measurements of g factor changes induced by thermal loading in the H1 interferometer Joseph Betzwieser et al. Commissioning
Cleaning
Core Optics
Auxiliary Optics
07 Jun 2011
T050074-x0 Optical Absorption in Initial LIGO Interferometers Stefan Ballmer et al. Commissioning
Cleaning
Core Optics
Auxiliary Optics
05 Jun 2011
T1100246-v1 iLIGO L1, H1 and H2 Interferometer Resonances Dennis Coyne System Engineering
Commissioning
Input Optics
Seismic Isolation
Core Optics
Auxiliary Optics
Suspensions
04 May 2011
T1000242-v2 Hierarchical Control Theory for Advanced LIGO Brett Shapiro Commissioning
08 Mar 2011
E1000500-x0 aLIGO SUS Test Stand and Electronics Testing and Commissioning Documentation Derek Bridges et al. Commissioning
Subsystem Test
Suspensions
28 Feb 2011
G080405-v1 Introduction to DC Readout Tobin Fricke Commissioning
Sensing and Control
14 Dec 2010
E1000510-x0 aLIGO SUS BSC Suspension Test Stand and Electronics Testing and Commissioning Documentation Derek Bridges et al. Assembly
Commissioning
Subsystem Test
Final Design
Suspensions
04 Oct 2010
E1000511-x0 aLIGO SUS HAM Suspension Test Stand and Electronics Testing and Commissioning Documentation Derek Bridges et al. Assembly
Commissioning
Subsystem Test
Suspensions
04 Oct 2010
T0900520-v4 Documenting Electronics using the DCC and the E-traveler Rich Abbott Commissioning
01 Oct 2010
G1000546-v1 Simulated Plant Approach Peter Michael Kalmus et al. Commissioning
Modelling
Sensing and Control
Basic R&D
15 Jul 2010
E1000002-v1 Certification for Viton for L1 HAM6 OMC damping struts Robert Taylor et al. Commissioning
Installation
Seismic Isolation
Incoming Inspection
Suspensions
11 Jan 2010
T0900518-v2 Quad Electronic and Optical Alignment Procedure Brett Shapiro Commissioning
15 Dec 2009
P0900119-v2 Commissioning of the tuned DC readout at GEO600 Hartmut Grote et al. Commissioning
29 Oct 2009
G0900349-v4 The Present and Near Future of LIGO Jeffrey Kissel Commissioning
Installation
Final Design
Meeting
Basic R&D
Upgrades
15 Jul 2009
G0900508-v1 The Status of GEO600 Hartmut Grote et al. Commissioning
01 Jul 2009
F080008-v8 Advanced LIGO Inventory Database PO/Line Parts Import Template Dwayne Giardina et al. Commissioning
Quality Assurance
Installation
Procurements
Operations Business
10 Jun 2009
G0900202-x0 Enhanced LIGO Commissioning Update Keita Kawabe Commissioning
17 Mar 2009
G0900141-v3 Performance of eLIGO Prototype HAM ISIs and improvements for aLIGO HAM ISIs Jeffrey Kissel Commissioning
Requirements
Modelling
Final Design
Seismic Isolation
Upgrades
13 Apr 2009
G080621-v1 The Status of Enhanced LIGO Aidan Brooks Commissioning
Seismic Isolation
02 Apr 2009
T0900113-v1 Recent Investigations/Modifications on the ISS Hartmut Grote Commissioning
Laser Systems
17 Mar 2009
G0900197-v1 Mitigation of environmental coupling for eLIGO Robert Schofield Commissioning
16 Mar 2009
G0900137-v1 Optimisation of the ISS Hartmut Grote Commissioning
Laser Systems
16 Mar 2009
E0900075-v1 Response to HAM-ISI Watchdog Committee Recommendations Jeffrey Kissel et al. Commissioning
Seismic Isolation
09 Mar 2009
T0810007-v2 Effect of ITM thermal lens in beam reflection Hiro Yamamoto Commissioning
Auxiliary Optics
27 Jan 2009

Number of documents found: 162


DCC Version 3.4.3, contact Document Database Administrators