This document presents series of tests (Phase II) performed on the ISI-BSC2 (BS).
First tests started in early August 2012, after BS installation and re-balancing of the ISI. Testing took 2 weeks (with breaks for Initial Alignment on the BS, the ISI was approved for Install on August 17th.
The cartridge install was done on September 7th 2012, after which payload was finalized and vibration absorption elements installed. Finally, Phase II-b testing was completed on October 10th and the dome was closed on October 11th.