09:00 – 09:30 |
Dynamic System Caltech:Purchase Order/Requisition |
|
|
09:00 – 10:00 |
Dynamic System Caltech:Proposal/Quote |
Caltech |
|
09:00 – |
SU-312a HSTS Suspensions Structure Fabrication:Close Out |
|
|
09:00 – 10:00 |
SU-312a HSTS Suspensions Structure Fabrication:Reports / Corrospondence |
|
|
09:00 – 12:30 |
SU-312a HSTS Suspensions Structure Fabrication:Change Order 2 |
|
|
09:00 – 11:00 |
SU-312a HSTS Suspensions Structure Fabrication:Bid Evaluation |
|
|
09:00 – 10:00 |
SU-312a HSTS Suspensions Structure Fabrication:Technical Documents |
|
|
09:00 – 13:00 |
SU-312a HSTS Suspensions Structure Fabrication:RFQ / RFP |
|
|
09:00 – 11:30 |
SU-312a HSTS Suspensions Structure Fabrication:Change Order 3 |
|
|
09:00 – 09:30 |
Dynamic System Caltech:Justification |
|
|
09:00 – 09:30 |
Dynamic System Caltech:Certification |
|
|
09:00 – 13:00 |
SU-312a HSTS Suspensions Structure Fabrication:Invoices & Packing Slips |
|
|
09:00 – 14:00 |
SU-312a HSTS Suspensions Structure Fabrication:Contract / PO |
|
|
09:00 – |
Dynamic System Caltech:Invoices |
|
|
09:00 – 12:00 |
SU-312a HSTS Suspensions Structure Fabrication:Change Order 1 |
|
|
09:00 – 11:30 |
SU-312a HSTS Suspensions Structure Fabrication:Change Order 4 |
|
|
09:00 – 10:00 |
SU-312a HSTS Suspensions Structure Fabrication:NSF Approval |
|
|